The 2025 Unit Overhaul at Pakistan Haveli O&M Project Successfully Concludes

2025-02-23


On February 22nd at 18:21, the unit at Pakistan Haveli O&M Project successfully reached full load, with excellent parameter readings, marking the successful completion of the unit overhaul work.

 

As a key task for the Pakistan Haveli O&M Project in 2025, the overhaul lasted 53 days and covered major turbine overhauls, intermediate overhauls of steam turbine generators, major boiler overhauls, and inspections of all auxiliary systems across the plant. A total of 307 routine maintenance tasks and 81 technical supervision tasks were completed.

 

During the overhaul, faced with challenges such as a tight schedule, heavy workload, and extensive overlapping operations, the maintenance team remained committed to the principles of "High Standards, Strict Requirements, Detail Orientation, and Pragmatic Implementation". Leveraging their technical expertise, they systematically resolved complex issues encountered during the process, intensified on-site inspections, strengthened supervision of critical steps and key milestones, and systematically advanced defect rectification for the unit. Ultimately, they completed all maintenance tasks safely, with high quality and efficiency.

 

After the overhaul, the unit's performance indicators have significantly improved, laying a solid foundation for its continued safe and stable operation. Moving forward, the project team will adhere to the work approach of "Mitigating Risks, Ensuring Compliance, Strengthening Management, and Enhancing Quality and Efficiency". They will focus on summarizing and integrating lessons learned from the overhaul, continuously optimizing O&M management, and driving high-quality contract fulfillment to further elevate the company's development to new heights.