Huafeng Weiye Company SA Zawar Project Achieves Great Success of the First Ignition of GT32 Gas Turbine
2014-10-27
At local time 14:30 (Beijing time 19:30) of October 23rd, 2014, Huafeng Weiye Company SA Zawar Project Block30 achieved success of the first ignition of GT32 gas turbine. The revolving speed was successfully raised to 3600rpm, and all operation parameters were in normal.
Since October 3rd, 2014, finishing the overhaul of the unit, the commissioning staff of Huafeng Weiye Company made great effort with all aspects on the site, cooperated with each other, successfully completed the commissioning tasks of gas turbine proper system and all auxiliary systems including gas turbine control-oil system, lub oil system, jacking oil system, metering air system, admission system and combustion system, prepared well for the ignition of GT32 gas turbine, and won recognition from the owner.
The successful ignition of GT32 gas turbine helped the project with more time to do the Block30 combined cycle commissioning and built firm foundation for the following work.

CONTACT US
TEL:0086-532-87098833
ADD:Building A, HTG Towers, 882-1 Tong An Road, Laoshan District, Qingdao, Shandong, China
E-mail:hfwy@sepco3.com
© COPYRIGHT Qingdao Huafengweiye Electric Power Technology Engineering Co., Ltd. | Powered by www.300.cn | Business license