·                   Yichun Garbage-Fired Power Plant is invested by Yinchun Zhongke Environment Protection Electricity Co.,Ltd and contracted by Sichuan Provincial Industrial Equipment Installation Co.,Ltd, Jilin Siping Yijian Group Co., Ltd and Heilongjiang Huayu Electric Engineering Co.,Ltd. The circulating fluidized bed garbage-fired unit project is designed by China GDE Engineering Co.,Ltd and the civil work and installation is done by Sichuan Provincial Industrial Equipment Installation Co.,Ltd, Jilin Siping Yijian Group Co., Ltd

·              The circulating fluidized bed garbage furnace can burn 400 tons of garbage per day and adopts garbage-coal mixture burning. The boiler is high temperature, high pressure, total steel frame, garbage-coal mixture burning, drum boiler, totally sealed arrangement with bag-type dust remover developed by Beijing Zhongke General Energy Environment Protection Co.,Ltd with a evaporation capacity of 35t/h. The steam turbine is N high-temperature, high-pressure, single cylinder, single bearing 15-4.9/0.98condensing steam turbine; the generator is air cooling QF-J12-2 generator with self excited static excitation system.

·                     The garbage trial burning commissioning is done in January, 2014 and the whole unit startup commissioning is scheduled in May, 2014. This project is the second garbage-fired power plant conducted by our company in China.